Internally
Internal partition
walls . This involved
the setting out
of the internal
of the building
and installing
metal stud partitions
,with a tape and
joint finish in
co-ordination with
other trades ,ie
mechanical, electrical
and ventilation
contractors
Internal Ceilings. This involved the supply
and
fit of grid
ceilings
in co-ordination
with other trades
,ie mechanical,
electrical and
ventilation contractors
Raised Access Flooring.
This involved the
supply and fit
of Kingspan Raised
Access Flooring
system throughout
the complete building.
Externally
Installation of
Fire Cavity barrier
External cladding.
The installation
of rail system
to the external
of the building
and installation
of cement board
to the rails
Installation of metal cills and flashing to
the
exterior of
the
building.